E-Line Pro

Inspirations

TRILUX and Van Dorp provide lighting for an ultra-modern laboratory

Eurofins Analytico: where precision and practice come together

Last year, a building that is anything but ordinary was erected along the A28 in Amersfoort. On a plot of over 13,500 m², Eurofins Analytico built a state-of-the-art, sustainable laboratory for soil and water analysis. A significant step forward for the global market leader in bioanalytical testing for food, water, the environment and pharmaceutical products, which is thereby reinforcing its growth ambitions.

Tendering with an eye for detail

For Van Dorp, who is responsible for the installations, and TRILUX, the supplier of the laboratory lighting, it was immediately clear: this is no ordinary working environment. “The workplace at Eurofins is unique,” begins Patrick van Boekel, project manager at Van Dorp. In laboratories, the nominal illuminance level on the worktop is 750 lux. As it is a high-risk environment, the emergency lighting must provide at least 10 per cent of that level. 75 lux for emergency lighting, on the other hand, is an extremely high level.

The partnership with Eurofins arose from a tender for the new-build project. Van Dorp, as the maintenance contractor for the current site in Barneveld, was asked to contribute ideas regarding the new location in Amersfoort. However, the original design specified a different lighting manufacturer. Van Boekel saw room for improvement and asked if he might propose an alternative. “Bearing in mind the current guidelines for laboratories and the client’s requirements, we carried out the calculations in collaboration with TRILUX.” “The result was a solution that was at least technically equivalent, but more costeffective.”

Centralised emergency lighting as a gamechanger

The alternative turned out to be not only financially attractive, but also technically more sensible. On the TRILUX side, project manager Marten Hilbrands was responsible for the implementation. During the preliminary phase, his colleague Vincent de Groot was involved in the planning and selection of products. The E-line Pro was selected in collaboration with Van Dorp. “We’ve been using the E-line Pro internationally for some time now, but it hasn’t yet been used in many projects in the Netherlands,” Marten begins. “This luminaire is ideal for Eurofins, particularly because of the central emergency lighting.”

The original design was based on decentralised emergency lighting fittings. Given the high levels of emergency lighting required, this proved to be a costly and, in some cases, even unfeasible option. “Many decentralised emergency light fittings simply don’t reach 75 lux,” adds Patrick. “And even if it does work, it’ll be extremely expensive.”

The E-line Pro makes it possible to combine multiple power supplies, including DALI, on a single rail. By switching to a centralised Eaton emergency power supply, savings were made not only on the initial investment but also on maintenance costs. Marten: “If you have to replace hundreds of batteries in individual light fittings every six years or so, it really disrupts the main process.” Especially if those light lines are high up and difficult to reach. "On paper, centralised emergency lighting sometimes seems more expensive, but in practice you easily recoup the cost."

Smart calculations for better lighting

As well as safety, visual comfort also played a major role. Eurofins set strict requirements for the UGR value (glare control) of the luminaires. “Our lighting calculations enabled us to demonstrate that we actually exceeded the specified requirements,” explains Marten. “This enabled us to reduce the light level to 90%, whilst the UGR value became even more favourable.”

He calls it a technical ‘trick’, as he puts it. But one that works. As a result, the final lighting plan provides a hassle-free, future-proof installation. Patrick adds: “The staff at Eurofins don’t notice a thing, apart from the fact that they’re working in very good lighting.” What’s more, dimming also has a positive effect on the lifespan of the light fittings. The specifications have been cleverly utilised in several ways. "That shows just how much product knowledge TRILUX has."

Building in a cramped ceiling space

In addition to the high technical requirements, the challenges posed by the structural conditions had to be considered. Patrick: “The Eurofins laboratories do not have a suspended ceiling, but a bare concrete ceiling. "All the installations are on display." “And that ceiling was literally packed to the brim,” said Marten. Ducts, pipes, cable trays, airhandling systems and various gas extraction systems presented quite a puzzle, with the light fittings still needing to be fitted in between them all. Acoustics were also a factor: sound-absorbing panels were hung between all the installations, and these had to be the same height as the light fittings.

Everything was worked out in detail in BIM. However, it became apparent during assembly that some of the planned heights were just not achievable. Marten continues: “Then you have to adapt, change your mindset and deal with reality in a creative way.” In consultation with the contractor, some of the light lines were hung slightly lower, without any noticeable effect on the quality of the light. Patrick: “TRILUX liaised quickly and professionally with all parties.” “As a result, the end result is sleek, practical and technically sound.”

Impressive figures

In total, Technische Unie supplied 297 E-line Pro luminaires, nearly 1,200 metres of continuous lighting and 10 ‘standard’ E-line luminaires on 70 metres of continuous lighting (IP64) for the automated warehouse. Patrick: “That warehouse is a world unto itself.” It is a huge hall containing robots and automated storage systems for soil samples. As there are no staff working there, the lights are right at the top. “Here too, a conscious decision was made to opt for Eaton centralised emergency lighting; once everything is up and running, you simply can’t access it anymore.” Spotlights and downlights have been installed in the offices, meeting rooms and communal areas, tailored to their specific use.

A sporting challenge

During assembly, the final, unexpected hurdle was overcome. The construction hoists had been re-moved, whilst lighting strip components measuring up to 4.5 metres and light fittings measuring 2.25 metres had to be hoisted up. What’s more, the staircases were cluttered with scaffolding, which made manoeuvring even more difficult.

Nevertheless, the teams from TRILUX, Van Dorp and the other construction partners were not deterred. Each component was carried upstairs and installed in the correct position. “Anyone who was up there had certainly had their workout for the day – or perhaps even the week,” says Marten with a laugh. The result is truly impressive: 1,200 metres of lighting strips, neatly mounted on the top floor, without com-promising the quality or the lighting design.

Solving problems together and taking the pressure off

Looking back, what stands out most is a sense of pride and appreciation for the collaboration. “Working together to find solutions and take the pressure off – I can’t think of a better way to describe TRILUX,” says Patrick. “I worked on this project for a year and a half in total and look back on a very pleasant collaboration. “We’ve all certainly achieved something wonderful here.”

Editors
Ann-Christin Blum
Online-Marketing
TRILUX
Categories
Health & Care
Industry
Human Centric Lighting
Light management
Quality
Sharing

Do you need help?

Headquarters

TRILUX GmbH & Co. KG

Postbox 1960
D-59753 Arnsberg

Phone: +49 29 32.30 1-0
Fax: +49 29 32.30 1-7 44
Email: info@trilux.com
Basics
Commerce
Tools and Services
TRILUX Intern

Shopping Cart